(Sesto Potere) – Rimini – 7 June 2024 – Excavation work on the Ravenna side has begun in recent days, aimed at the construction of the vehicular underpass, which will allow the direct connection of via Euterpe with via della Repubblica. In the next few weeks the preparatory works on the sea side will be completed, which will allow the continuation of the excavations on the other front as well.

With the completion of the head curbs, currently nearing completion, preparatory to the excavation of the diaphragms (i.e. the 25 m deep containment bulkhead), the actual excavation of the underpass is now proceeding. A very important phase, as it is crucial to speed up the opening of traffic between Euterpe/Repubblica streets, expected in the provisional phase with single-lane transit, by the end of the summer.

All the works, at this moment, are in fact concentrated on via Euterpe, where the sewerage systems, the civil plant works and the maintenance yard for the lifting systems will be completed. This is the most important work of the stretch, consisting of 250 meters of ramps and an underpass of approximately 31 metres, which will allow the elimination of the traffic light previously necessary to allow access to state road 16 from via della Repubblica.

The works, as is known, fall within the scope of the works carried out by Autostrade per l’Italia, for an investment of approximately 7 million euros, and required the closure of via Euterpe for the construction of the new intersection between state road 16, via of the Republic and San Marino highway.

A construction site which is also connected to the works for the creation of a new cycle/pedestrian path with three underpasses for crossing the roundabout and via Euterpe, which will connect the upstream area with the seaside area, joining the already existing cycle/pedestrian path inside the Giovanni Paolo II park (La Cava park).
In reference to this work, which will allow an important urban re-stitching, the walls of the western cycle are currently being completed, i.e. the part of the underpass between the new roundabout and the mountain side of via Euterpe, where the connection is planned with those who come from the Garden.

At the same time, the manhole that crosses via Euterpe orthogonally was completed. A new hydraulic collector of the old Ausa stream, with a route parallel to the cycle path, which involves the construction of the hydraulic crossing, allowing the mountain-sea continuity of the stream.

On the work front on the roundabout, in recent weeks the technical discussions between the Municipality, Anas and ASPI were concluded to carry forward the process of changing the design of the entrances to the roundabout, aimed at making the two-lane entrances, not foreseen in the configuration, permanent. initial. The works relating to this construction phase will be started at the end of the process.

 