FiumicinoThe new Market PlateaticoThe Cafe and attached toilet And ticket office/stop bus they will be air-conditioned, in the summertime And in winterthanks to air conditioners which will be installed on the 4 pre-fabricated modules which will occupy approximately 250 square meters of useful space in total.
The structure is located near via della Foce Micina snc. Approximately €53,000 of the project received the definitive green light from the municipal technical office of Fiumicino with authorization no. 951 today, 14 June 2024. “Interventions and energy certification of the buildings of the new Plateatico, approval of the executive project and economic framework”.
Fiumicino is greener, new market, bar and bus stop air-conditioned with solar energy
The project was drawn up by the well-known multinational Engie. It involves the construction of summer and winter air conditioning systems. With the help of photovoltaic systems that will be installed above the 4 pre-fabricated modules. That is, the real estate structures that will constitute the “New Mercato Plateatico” in Via della Foce Micina. An area located near the exchange and bus parking lot, located in Fiumicino.
The innovative project of the multinational Engie
“The relief – we read in the project by the Engie company – is aimed at identifying the best design compromise of the building-plant system. With the aim of achieving the following objectives.
The thermo-hygrometric comfort of occupied environments. The flexibility of use of the system. The project aims to optimize the management of the summer and winter air conditioning system. There will mainly be the use of renewable energy sources.
The municipal contract
The municipal contract has as its object the construction of 4 monobloc prefabricated wooden buildings with the following nomenclatures and intended uses. The first is module A, it is dedicated to recreational activities. Bar, with a total surface area of 90 m2. The second is module B. It will instead be used for: toilets, with a total surface area of 45 m2. The third is module C: New Market management services, with a total surface area of 50 m2. The fourth and last is module D: ticket office, with a total surface area of 50 m2.
This document defines the plant components, from the main equipment to the distribution network. The sizing of air conditioners is sized for summer energy consumption and winter energy losses.