Torre del Greco – Work continues for the collection of wastewater, steps forward towards the completion of the work

Torre del Greco – Work continues for the collection of wastewater, steps forward towards the completion of the work

Important steps forward in the works edited by Gori for the collection of wastewater from Torre deL Greek to the Foce Sarno purifier.

In fact, some important interventions have been completed in via Campanariello and via Pagliarone, with the completion of the microtunnel sectionLLeng of the sewer collector that will transport the wastewater coming fromthe purifierthe of San Giuseppe alle Paludi And English Villa towards The purifiesbull district of Foce Sarno. Yesterday morning, in the presence of the Mayor of Torre del GrecoLuigi Mennella, and the leaders of Gori and Ente Idrico Campano, the inspection to take stock of the important infrastructure created with techniques No Diginnovative, safe and respectful of the territory; to follow, the visit to construction site in via Fusco, In the cmunicipality of Torre Annunziata, where completion is expected by the end of September dthe last one microtunnel sectionLeng, which will allow connection to the existing district collector.

Today’s intervention concerns the completion of the microtunnellling that from French quarry comes away Pagliarone. A work of approximately 300 meters in length, excavated with the microtunnel techniqueLeng in a very complex geological context, with high material hardnessof volcanic origin got through. We have completed this complex intervention, also drastically reducing the construction times of the recovery well, over 15 meters deep from the ground level. After the recovery of the machine present in the well, the lifting station will be completed And of all civil workswith the installation delle electromechanical equipment, to lift sewage towards via Caravellthewhere the works are already completed. The drains will be eliminated by the end of 2024 of Villa Inglese and powershermitage all preliminary treatments of San Giuseppe alle Paludi, always with a view to improving the bathing ability of the coast of Torre del Greco and Torre Annunziatadeclares the RUP of the intervention, Giovanni De Simone.

More generally, the project for Torre del Greco, financed by the Campania Region for 35 million euros and of which Gori is the implementing body, is aimed at the construction of the collector sewer system which will allow collectionmanage the wastewater coming from the entire municipal territory and convey itfor the final purification treatment, to the plant Mouth Sarno” located to Castellammare di Stabia, as provided for by planning regional.

We are close to taking another decisive step towards the goal of providing Torre del Greco with an increasingly blue sea. This is done with a work of high engineering value: self everything will go as planned, in the autumn we will have the area, once served by the Viale Europa purifier, completely collected at Foce Sarno. In practice, by the end of 2024 approximately 40% of the wastewater produced by the citizens of Torre di Torre will be destined for the main plant. ANDntror the conclusion of 2025Therefore, all wastewater collection works will be completed: that is will contribute to further improve the quality of marine waters, which are already excellent in many places. Finally, I ask the citizens a little patience in enduring any possible inconvenience” declares the Mayor of Torre del GrecoLuigi Mennella.

With these interventions we are taking a further step, important step forward in our environmental recovery plan which projects us towards the recovery of the entire coast of the Gulf of Naples. The microtunnelling technology goes in the direction of guaranteeing the functionality of the work, avoiding the inconveniences associated with surface excavations and combining efficiency and innovation to outline an increasingly modern and advanced perspective of protection of the water resource, as part of the virtuous path that sees the Campania Water Authority as a protagonist in synergy with the Campania Region and Gori. It was exciting to watch the release of the mole and it was not at all obvious, given the considerable complexity of the ongoing intervention, which is the result of professionalism and skills consolidated over time. We have set ourselves the ambitious goal of making the entire stretch of coast suitable for bathing, which has been awaited for decades: a historic goal, now ever closer” concludes the President of the Campania Water Authority, Luca Mascolo.

 