“Waiting for the commitments of the DG of ASL Bat”

The Committee for the New Hospital of Andria asks the general management of the ASL Bat if the contractual appendix has been signed with the designers.

«On the outcome of the meeting of the 1st commission of the Regional Council of Puglia, the Mayor of Andria communicated to us, among other things, the following…
“On the timing of the procedure, ASL Bat, as the contracting authority, has communicated that within 10 days they will sign the contractual appendix with the designers.
From the formalization, the 90 days that the Rup will impose on the designers for their obligations will start.
To save time, ASL and Asset will work together in this phase to carry out contextual checks on the project progress”.

“As we know, the commission meeting was held on May 6th. Today we are on May 18th.
The 10 days have well passed. Since there was no communication, we wonder if, as stated, the general management of ASL-BAT proceeded with the signing of the contractual appendix with the designers. Compliance is of vital importance for the continuation of the administrative process within the expected timescales. We therefore ask that the management of the ASL officially communicate to the city community the fulfillment of the commitment made on 6/5/2024.
There have been so many delays and non-compliances accumulated up to now that it has led to a timely verification of the commitments undertaken by each function involved in the procedure for the construction of the New Hospital of Andria”, concludes the note from the Committee for the New Hospital of Andria.

 