Municipality of Naples – Traffic devices in the city for works

Municipality of Naples – Traffic devices in the city for works
Municipality of Naples – Traffic devices in the city for works
The Permanent Conference of Services for road construction sites and events, in which all the Municipalities, Services and bodies involved are regularly invited to participate and which meets on a weekly basis, approved in the presence of representatives of the Local Police Service, the Roads, Roads and Traffic Service, del Territorial Hydrogeological Defense and Reclamation Service, of the Event Management Service and DA Maradona Stadium, of Municipalities 4 and 6 and of Metro di Napoli Spa, some construction sites that will affect the following roads:


From 04/29/2024
, within the framework agreement “Maintenance interventions also with mountaineering techniques on walls and slopes aimed at carrying out safety works by dismantling small boulders, bricks and/or stones, cleaning from weeds, placing containment nets and renovating the wall facing“work has begun to secure the wall overlooking the Coroglio descent near the entrance to the Seiano Cave. The scaffolding set up for the works, which will last approximately 60 days, occupies exclusively the pavement without obstructing traffic.

On 10/05/2024, in anticipation of the passage of the stage of the Giro d’Italia on 12/05/2024, the construction site will be temporarily removed to be restored on Monday 13 May next


On 02/05/2024
excavation works will be carried out by ANM for the laying of cable ducts serving the traffic light system which regulates pedestrian crossings in via Pietro Castellino at civil height. 137. For these works a particular traffic device has already been established with OD n. 787 of 04/26/2024 which provides for the alternating one-way system regulated by moving traffic lights and traffic lights, for 30 meters upstream and downstream of the traffic-lighted pedestrian crossing located at the civ. 137 and the suspension of said pedestrian crossing and the ANM bus stop on the right side towards Via D’Antona, located approximately 20 meters from civ.137.


From 6 to 09/05/2024
two excavations will be carried out by ABC for the laying of water pipes in via Justiniano, the first at the civ. 283 and the second at the intersection with via Cassiodoro. The works will be carried out without interruption to vehicular traffic, during daytime starting from 09:00 to allow the morning flow of vehicles.


From 6 to 14/05/2024
for the connection of two utilities branching from the existing network, the company 2i ReteGas Spa will carry out excavation works in via Provinciale delle Brecceat the height of numbers 108, 118, 100, 80, 103/A, 98/A according to the following methods:
– 06/05/2024 – The first excavation will be carried out at the civ. 118. The works will be carried out in three phases, the 1st and 2nd phase will concern the roadbed, occupying half the carriageway at a time, thus avoiding the interruption of vehicular traffic. Subsequently, we will continue on an area outside the roadway to be carried out in a single phase with the temporary prohibition of pedestrian transit. The excavation will end near the boundary wall of the building;

– 07/05/2024 – The second excavation will be carried out at the civ. 108 with the same methods described for the works at the height of the civ. 118;

– 05/08/2024 – The third excavation will be carried out at the civ. 100. The works will be carried out in two phases, occupying half the road at a time, thus avoiding the interruption of vehicular traffic. Subsequently, we will continue on an area outside the privately owned roadway;

– 05/09/2024 – The fourth excavation will be carried out at the civ. 80 with the same methods described for the works at the height of the civ. 100.

– 13/05/2024 – The fifth excavation will be carried out at number 103/A. The works will be carried out in a single phase and it is agreed that the works can be carried out with open vehicular traffic using part of the roadway left free by the works with only the narrowing of the same.
– 05/14/2024 – The sixth excavation will be carried out at number 98/A. The works will be carried out in two phases, occupying half the road at a time, thus avoiding the interruption of vehicular traffic.

All work will be carried out during daytime.

On 05/09/2024for the connection of two utilities branching from the existing network, the company 2i ReteGas Spa will carry out excavation works in via Ravello, near the confluence with via Sorrento. The works will be carried out partly on the pavement and partly on the road with the establishment of an alternate one-way system regulated by traffic lights.


From 05/13/2024 to 06/01/2024,
excavation works will be carried out for the installation of an underground MV electricity line section, by e-Distribuzione Spa, in vico Lammatari, Traversa Lammatari and via Sanità. The works will be carried out starting from the Enel substation present in Vico Lammatari, in front of number 37 of the same, to continue up to the intersection with Traversa Lammatari and to arrive on Via Sanità and end at the height of the existing Enel substation, located next to it. at the Decò supermarket. During the execution of the works, both Vico Lammatari and Traversa Lammatari will be closed and, alternatively, vehicles can be directed towards Via Sanità.


From 05/13/2024 to 06/21/2024,
we will proceed with the construction of the ABC maneuvering room for the fire-fighting supply of the Capodichino Station, CDN/Capodichino section of Line 1 of the Naples Metro in viale Umberto Maddalena at the confluence with via Pinto, with open traffic, in several phases and in the following ways:

– Phase 1 – from 05/13/2024 to 05/17/2024;
– Phase 2 – from 05/20/2024 to 05/24/2024;

– Phase 3 – from 05/27/2024 to 05/31/2024;
– Phase 4 – from 03/06/2024 to 07/06/2024;
– Phase 5 – from 10/06/2024 to 21/06/2024.
For Phases 1 and 5, the occupation of a lane of Viale Maddalena is expected, with the direction of travel towards Secondigliano, in the stretch between number 33 and the confluence with Via Pinto. During these two phases, the ANM bus stop n. 1213 present there, will be temporarily moved after number 11 of viale Umberto Maddalena.

During Phases 2, 3 and 4 the works will be carried out on viale Maddalena crossing via Pinto, occupying a portion of the roadway at a time, thus avoiding the interruption of vehicular traffic. At the end of each individual phase the construction site will always be demobilized and re-set up at the beginning of the next phase, for these operations motor vehicles will always be used to manage vehicular traffic.

From 05/13/2024 to 09/06/2024, excavation works will be carried out for the installation of an underground MV electricity line section, by e-Distribuzione Spa, in via Gaetano Bruno, via del Pascone, via Giuliano da Maiano, via Giuseppe Buonocore, piazza Salvatore Lo Bianco, via Vesuvio, via Giovanni da Procida, via Nicola Fraggianni.
The works will be carried out with open traffic according to the following phases:

– from 13 to 14/05/2024 from via Gaetano Bruno, in the stretch between the A. Betranelli nursery school and the intersection with via Giuliano da Maiano;

– from 15 to 16/05/2024 the works will be carried out along via del Pascone in the stretch between via Gaetano Bruno and via Giuliano da Maiano;
– from 17-27/05/2024 the works will continue in via Giuliano da Maiano, in the stretch between via Gaetano Bruno and via Giuseppe Bonocore;

– from 05/28/2024 and 06/05/2024 the works will take place on via Giuseppe Bonocore in the stretch between via Giuliano da Maiano and piazza Salvatore Lo Bianco
– from 6 to 13/06/2024 the works will continue on and in piazza Salvatore Lo Bianco in the stretch between via Giuseppe Bonocore and via Vesuvio;

– from 14 to 17/06/2024 on Via Vesuvio crossing between Piazza Salvatore Lo Bianco and Via Giovanni da Procida, the works will be carried out with open crossing traffic, using half the roadway at a time and at the end of the daily works the construction site will be decommissioned and the usual traffic conditions restored;

– from 18 to 28/06/2024 the works will continue on via Giovanni da Procida up to the intersection with via Nicola Fragianni;

– from 1 to 10/07/2024 the works will end in via Nicola Fragianni in the stretch between via Giovanni da Procida and via Luigi Landolfi.


From 05/22/2024 to 06/30/2024
, to allow the demolition of the building located in the avenue to take place Colli Aminei n. 11/A scaffolding will be set up which will occupy the entire pavement in front of the building undergoing intervention. The works will be carried out without interruption of vehicular trafficTo allow the transit of pedestrians, existing pedestrian crossings will be used, upstream and downstream of the occupied area. Furthermore, on the opposite road front a protected pedestrian walkway has already been set up for other ongoing works regarding the demolition and reconstruction of the Ovidio Decroly nursery school in viale Colli Aminei civ. 18/B.

Regarding the events:

The 05/01/2024 the rally of historic cars will take place “Naples Grand Prix – Posillipo Circuit XXVII edition”, starting from Virgiliano Park and arriving at Villa Imperiale in via Marechiaro.

For this event it was established with OD n. 786 of 04/26/2024, a particular traffic device which provides, from 9:00 to 13:30, and in any case until the needs cease, the ban on vehicular transit in via Virgilioexcept for vintage cars and motorbikes participating in the event, emergency and rescue vehicles and law enforcement vehicles.


From 2 to 06/05/2024
the second edition of. will take place Grand Prix – Jet Ski Grand Prix 2024” at Caracciolo seafront and Diaz roundabout.


For this event it was established with OD n. 788 of 04/26/2024, a particular traffic device which provides,
from 10:00 am on 02/05/2024 to 12:00 pm on 06/05/2024, the suspension of the cycling mobility route in via Caracciolo, in the stretch between viale Dohrn and piazza della Repubblica.


On 04/05/2024
to allow the carrying out of the “Translation of the relics of San Gennaro“, religious procession which starting from the Cathedral will reach the Basilica of Santa Chiara, it will be necessary to establish a particular traffic device which will provide, starting from 4.00 pm and until the needs cease, a ban on vehicular transit, in the sections from time to time once affected by the procession along the following streets:
Via Duomo (Cathedral height), Via San Biagio dei Librai, Piazzetta Nilo, Piazza San Domenico Maggiore, Via Benedetto Croce (Church of Santa Chiara-courtyard).

Furthermore, from 3.00 pm until no longer necessary, the suspension of paid parking spaces (blue lines), parking for motorcycles, parking for loading/unloading goods and parking reserved for taxis in Via Duomo (tract from Via Tribunali to Piazzetta San Giuseppe dei Ruffi), as well as the establishment of the parking ban with forced removal in Via Duomo (tract from Via Tribunali to Piazzetta San Giuseppe dei Ruffi).

 