10 construction sites underway on the hills of Bologna. We start in June

10 construction sites underway on the hills of Bologna. We start in June
10 construction sites underway on the hills of Bologna. We start in June

HERE TO SUBSCRIBE TO THE BOLOGNATODAY WHATSAPP CHANNEL

Over 10 construction sites are underway on the Hills to resolve the most critical landslides caused by last May’s flood, after temporary interventions worth around 1 million euros carried out as a matter of urgency in 2023.

First works starting in June, expected to be completed by autumn

An investment of 7,620,000 euros which will see the first works start in the month of June, barring unforeseen circumstances, with conclusion in autumn in via dei Colli, via di Sabbiuno and via di Monte Albano. Work has also started in June Via degli Scalinian area from which complaints have recently been raised by some residents about the dangers related to trafficcurrently being put to the test.

This is what Palazzo D’Accursio says, adding that the project via delle Lastre is also nearing completion and, once the necessary authorizations have been obtained, work will start by the end of the summer. As well as the Via delle Torriane project which is being developed by the Consorzio di Bonifica Renana which has been given the task of implementing it by the Municipality of Bologna.

Via degli Scalini closed by the flood, the residents: ‘We need to intervene quickly, we feel like second-class citizens’

Second group of works starting after the summer

Same process for the works in via del Ravone, among the interventions that present the greatest critical issues even if – the Bolognese Municipality points out – the road is currently safe and passable, which will start in September and October.

A second group of interventions, for 4,160,000 euros, is being finalized with geologists and designers who are working on the technical-economic feasibility projects for via della Fratta, del Poggio, del Paleotto and Barbiano.

The conclusion of designs is expected for end of Septemberthen we will proceed with the awarding of the works whose start is expected in the first months of 2025.

What stage are construction sites in the Bolognese area at 11 months after the flood

 