PESCARA. The infernal chaos on the A14 has its days numbered. At 6am next Friday, May 31st, the twelve motorway construction sites which cause endless queues, long waits and inconvenience will be suspended. This time the truce will last 100 days, starting from June until the first ten days of September. But before the stop, starting this evening, new night construction sites will be added to the work carried out during the day which will end up complicating the situation on the Abruzzo stretch of the A14 during the last week before the long break.
THE TWELVE WORKSITES
We are publishing a preview of the map of the construction sites that will be interrupted. The Autostrade per l’Italia company has listed them as follows.
1)Section between Roseto degli Abruzzi and Atri-Pineto towards Pescara between km 345+600 and 349+000 for the modernization of the Colle Marino Sud tunnel.
2) Section between Pescara Nord and Atri Pineto towards Ancona between km 354+100 and 353+200 to redevelop the bridge edge barriers of the Santa Maria Nord viaduct.
3) Section between Pescara Nord and Atri Pineto in the direction of Ancona between km 359+600 and 352+000 for the modernization and requalification works on the bridge edge barriers of the Cerrano Nord viaduct and for the adaptation of the safety plan of the Fonte da Capo Nord tunnel.
4) In the stretch between Val di Sangro and Lanciano towards Pescara and Bari between km 421+300 and 419+000 for restoration of the counterbank wall.
5) In the stretch between Roseto degli Abruzzi and Giulianova-Mosciano Sant’Angelo towards Ancona between km 339+700 and 334+800 for maintenance works in the San Marco Nord tunnel.
6) In the stretch between Roseto and Giulianova-Mosciano Sant’Angelo towards Ancona between km 343+900 and 343+090 to redevelop the bridge edge barriers of the SS150 Vomano viaduct.
7) In the stretch between Pescara Ovest and Pescara Nord between km 372+400 and 368+200 for slope consolidation works and safety barrier upgrading.
8) In the section between Pescara Ovest and Pescara Sud towards Ancona and Pescara between km 391+600 and 387+500 for works on the joints of the Alento viaduct.
9) Section between Ortona and Pescara Sud towards Pescara between km 403+900 and 398+100 for waterproofing and paving works on the Riccio and Lupo Nord viaducts.
10) In the stretch between Vasto Nord and Val di Sangro towards Pescara and Bari between km 428+000 and 425+700 for maintenance work on the safety barriers.
11) In the stretch between Vasto Nord and Vasto Sud towards Bari between km 446+700 and 451+300 for the modernization of the Giustina Sud viaduct.
12) In the stretch between Vasto Nord and Vasto Sud towards Pescara and Bari between km 435+800 and 438+000 for the rehabilitation of the joints of the Sinello Sud viaduct.
NIGHT CLOSURES
We start today with this notice: «On the A14 Bologna-Taranto, to allow cable laying and maintenance work, from 11pm on Sunday 26th to 5am on Monday 27th May, the section between Pescara west Chieti And Pescara south Francavillain both directions – Bari and Ancona/Bologna.
Alternatively, the following itineraries are recommended: towards Bari: after the obligatory exit at the Pescara Ovest Chieti station, take the SS16 Adriatica towards Foggia and return to the A14 at the Pescara Sud Francavilla station; towards Ancona/Bologna: after the obligatory exit at Pescara sud Francavilla station, take the SS16 Adriatica towards Ancona and return to the A14 at Pescara Ovest Chieti».
Also on the A14, to allow for paving works, on the two nights of tomorrow and Tuesday, from 10pm to 6am, the Teramo Giulianova Mosciano Sant’Angelo station, outgoing for those coming from Bologna/Ancona and Bari/Pescara. Alternatively, we recommend exiting at the following stations. For those coming from Bologna/Ancona: Val Vibrata; for those coming from Bari/Pescara: Roseto.
The closure program has also been updated Vasto Nord station, which will be carried out from 10pm tomorrow to 6am on Tuesday, to allow the removal of the construction site area on the “Sinello” viaduct. Alternatively, we recommend entering the Vasto Sud station.
To allow the reconfiguration of the construction site area on the “Santa Maria” and “Marinelli” viaducts and maintenance work on the systems in the “Solagne” tunnel, from 10pm on Wednesday to 6am on Thursday 30 May, the section between Pescara north City of Sant’Angelo And Atri Pineto, towards Ancona/Bologna. Alternatively, after the obligatory exit at Pescara Nord station, follow the SS16 Adriatica towards Ancona and return to the A24 at the Atri Pineto station.
A final notice closes the long list: «To allow activities as part of the redevelopment works of the safety barriers of the “SS150 del Vomano” viaduct, from 10pm on Thursday to 6am on Friday 31 May, theat Roseto degli Abruzzi station, entering Pescara. Alternatively, we recommend entering Atri Pineto station.”