Mugello flood: regional table starts, 30 million for the Faentina railway line

Mugello flood: regional table starts, 30 million for the Faentina railway line
Mugello flood: regional table starts, 30 million for the Faentina railway line

Wednesday 8 May the point was made in the Region on thepublic and private reconstruction activities in Alto Mugello after last year’s flood.

The president of the Region participated in the table that took place at Palazzo Strozzi Sacrati, as sub-commissioner for reconstruction, with the structure of the extraordinary commissioner Francesco Paolo Figliuolo and local administrations affected by bad weather between 15 and 17 May 2023.

Also present were representatives of the Metropolitan City, of the Municipalities of Marradi, Firenzuola, Londa and San Godenzo, Palazzuolo sul Senio, of the Rhineland Reclamation Consortium and that of Western Romagna as well as the technicians of Tuscany region.

The meeting was an opportunity for the implementing bodies to take stock of the status of progress of restoration and repair interventions for the most urgent needs. They were insured by Tuscany region respectively 1,873,000 euros for hydraulic defense interventions implemented by the Reclamation Consortia e 22,533,390 euros for road restoration works and road infrastructures implemented by the Municipalities and the Metropolitan City of Florence.

In addition to guaranteeing maximum availability and collaboration with respect to the issues put on the table by the local administrations, the commissioner structure has also announced the allocation of financial resources for 30 million euros for the works to be carried out on the Faentina railway line.

The start of the tender procedure for the awarding of the works is scheduled for the month of September 2024 and thestart of work by mid-2025. From the meeting it emerged that the entities are carrying out all the activities necessary to start the construction sites within the current year.

Furthermore, compared to the package of interventions already authorized, by the summer, it will be approved by the commissioner structurethrough the reuse of Pnrr funds referred to in line 2.1a, a remodulation and integration of the financial resources already allocated for over 50 million euros which will, among other things, allow the planning of further interventions, giving a clearly decisive response compared to the framework of the critical issues arising from last May’s event.

A review was also made of the state of progress of the contribution procedures in favor of private individuals and productive activities, with respect to which the maximum agreement was renewed to accelerate as soon as possible the preliminary investigation process to be carried out to ensure that the contributions reach the requesting parties but, at the same time, also to raise awareness among citizens of the possibility of still being able to submit an application, taking into account that the timing is still open.

 