After having verified some critical execution issues that have caused significant problems for traffic and citizens, we have asked the various service companies that have carried out scheduled and/or urgent work in the city for a rigorous timetable for the timely and definitive restoration of the asphalt.
A systematic execution schedule (including night-time) has been drawn up to minimize the inevitable inconvenience to the population and mobility while ensuring the safety of the construction sites and the workers involved.
The first interventions have already been carried out in recent days on the Lungomare near the Grand Hotel Salerno and in Torrione Alto in the streets Vestuti, Granato, Quagliariello.
The next batches of work are planned in the following streets:
Via dei Casali from 3rd to 4th July
Via Calata San Vito from 3rd to 4th July
Via Francesco Crispi from 3rd to 4th July
Via Trucillo from 5th to 8th July
Via Francesco P. Lettieri from 5th to 8th July
These works will be carried out during the night hours between 10.00 pm and 6.00 am, excluding Saturdays and Sundays.
A second phase of works will involve via San Leonardo trav. Migliaro, Ghandi, Visco, SS 18 starting from July 15. The detailed program of the subsequent works will be communicated progressively in the next few days.
The mayor of Salerno Vincenzo Napoli wrote this on his Facebook profile