Reconstruction of schools in L’Aquila, the point: 18 interventions for over 90 million euros

Reconstruction of schools in L’Aquila, where are we at? The progress dossier has been published. A total of 18 interventions were planned, of which 3 were completed. Among the works in the planning phase are the two school centers of Sassa and Collemaggio.

The reconstruction in L’Aquila also and above all passes through the schools. 15 years after the earthquake, what is the situation?
It was published on dossier on the progress of the reconstruction of the city schools. Going to look at the numbers, the Municipality of L’Aquila has provided, at the expense of reconstruction funds, 16 interventions for a total requirement of 93 million and 144,986.32 euros. The institution also planned the construction of 2 interventions using PNRR resources, for a further 7 million and 995,000.00 euros. The total requirement borne by the funds of the reconstruction of L’Aquila schools is financed for 59,841,580.00 euros and for 33,303,406.32 euros, with the update of the annual plan of line 2, by CIPES of March 29, 2023.

Pettino-Vetoio nursery school, the construction site returned

The last construction site returned, last February, was that of Pettino-Vetoio school in via Madonna di Pettino.
5
modern classrooms, each of a different colour, on a surface area of ​​approximately one thousand m2, ready to welcome 118 nursery school children for the next school year. Jobs, started in March 2022after the symbolic laying of the first stone – for an amount of approximately 2 million euros – will now allow us to have a modern and technological nursery school. In addition to the spaces for teaching, canteen and teachers, a covered area is foreseen for the carrying out of “free” activities of the pupils, such as, for example, physical education.

18 total interventions planned, for a total of €101,139,986.32. This is the implementation status:

Interventions completed

NURSERY AND PRIMARY SCHOOL TEN C. TARANTA – LOC. ARISCHIA €2,605,680.00
MARIELE VENTRE PRIMARY SCHOOL – PETTINO €6,903,462.00
“PETTINO VETOIO” SCHOOL CENTER – LOT 1 – €2,400,000.00
For a total of €11,909,142.00

Interventions with works in progress or contracted

SAN SISTO SCHOOL CENTER – SANTA BARBARA €6,524,685.00
TORRETTA GIGNANO S. ELIA SCHOOL CENTER €5,200,000.00
PETTINO VETOIO SCHOOL CENTER – LOT 2 – €2,600,000.00
BAGNO GRANDE NURSERY SCHOOL €1,300,000.00
CELESTINO V PRIMARY SCHOOL €2,400,000.00
SAN GIOVANNI BOSCO NURSERY SCHOOL €731,188.00
MAZZINI MIDDLE SCHOOL €10,741,565.00
NEW BUILDING OF THE F. ROSSI PAGANICA PRIMARY SCHOOL €5,850,000.00
CONSTRUCTION OF THE NEW PRESENTER SCHOOL INSIDE THE SCHOOL CENTER OF THE FRACTION OF PAGANICA IN L’AQUILA €2,145,000.00
For a total of €37,492,438.00

Design interventions

SASSA SCHOOL CENTER €12,000,000.00 executive approval
PIANOLA ELEMENTARY SCHOOL €3,792,406.32 final approval
DANTE ALIGHIERI PAGANIC MIDDLE SCHOOL €6,796,000.00 executive being updated
PRIMARY AND CHILDHOOD SCHOOL GIOVANNI XXIII €9,450,000.00 final approval
COLLEMAGGIO SCHOOL CENTER 18,600,000.00 € DEPT
COPPITO ELEMENTARY SCHOOL €1,100,000.00 Executive approval
For a total of €51,738,406.32

To find out the details of the interventions, consult the dossier on the reconstruction of schools in L’Aquila at this link.

Reconstruction, 50 million for 12 schools hit by the 2009 earthquake between L’Aquila and Cratere

 